interrupted
A structure with construction paused for three months or officially stopped earlier, subject to the corrective-work exception.
A structure is interrupted when there is a significant lapse in construction. This status does not apply to proposals - only to structures where construction has already begun.
This status is assigned once construction has stopped for 3 months, or when an official announcement of construction stoppage has been made (whichever comes first).
When construction is halted in order to correct errors, a project should not be listed as interrupted even if progress stops for 3 months or longer, unless resumption of progress is not scheduled to resume promptly thereafter.
interrupted Photos
Related definitions
-
foundation work
The construction phase from placement of the first foundation element until the structure begins rising above ground. -
frame assembly
The construction phase in which the framework rises above the base and takes shape, including the subterranean exception. -
topped out
The construction phase after completion of the structural framework and maximum dimensions but before readiness for use.