A structure with construction paused for three months or officially stopped earlier, subject to the corrective-work exception.
A structure is interrupted when there is a significant lapse in construction. This status does not apply to proposals - only to structures where construction has already begun.
This status is assigned once construction has stopped for 3 months, or when an official announcement of construction stoppage has been made (whichever comes first).
When construction is halted in order to correct errors, a project should not be listed as interrupted even if progress stops for 3 months or longer, unless resumption of progress is not scheduled to resume promptly thereafter.