Work on an unfinished structural frame resumes after an irregular stoppage lasting at least 10 days.
Resumption of framework construction on a structure occurs when a structure has already begun rising above its base but its frame has not yet been completed, and when work resumes after an irregular pause of at least 10 days. If the stoppage was entirely regular or based on a holiday, then neither it nor the resumption should be registered as events. This event changes the status of a structure from on hold back to frame assembly.
The frame must already have risen above the base and remain unfinished. Resuming work before that stage is foundation work resumes, while a frame completed before the pause calls for final-phase work resumes.